An enterprise/private person developing any kind of project above mentioned is required to secure a Preliminary Approval/Locational Clearance at the Municipal Planning and Development Office prior to the start of the project. This should be done before the start of construction/development to ensure that the project is allowed in the chosen location and is in conformity with the Comprehensive Land Use Plan and Zoning Ordinance of the municipality.
Office or Division: Office of the MPDC
Classification: Simple
Type of Transaction: G2C - Government to Client
Who may avail: Any person/entity, with lot/property within the municipality
SECURE an Application Form and List of Requirements
Agency Actions:
Issue Application Form and List of Requirements
Fees to be Paid: None
Processing Time : 1 minute
Person Responsible:
Zoraida R. Caringal
Rhea A. Buendia
SUBMIT duly accomplished application form with complete documents/requirements
Agency Actions:
RECEIVE & REVIEW application form and request submitted by the applicant.
Schedule date for site inspection
Fees to be Paid: None
Processing Time : 15 minutes
Person Responsible:
EnP Monalisa Robledo
Agency Actions:
CONDUCT site inspection
Fees to be Paid: None
Processing Time : 4 hours
Person Responsible:
Engr. Marlino Babida
Agency Actions:
I. PREPARE result of inspection with proper recommendation/s
II. For reclassification: Endorse to MDC for appropriate action/ recommendation to SB
III. Prepare PALC
Approve/Sign PALC
Fees to be Paid: None
Processing Time : 30 minutes
Person Responsible:
I. Engr. Marlino Babida
II. EnP Monalisa Robledo
III. Rhea A. Buendia
Zoraida R. Caringal
EnP Monalisa B. Robledo
Claim Locational Clearance
Agency Actions:
Release approved PALC
Fees to be Paid: Refer to Revised Revenue Code 2013
Processing Time : 1 minute
Person Responsible:
Zoraida R. Caringal
Rhea A. Buendia
Total Time:
~
4hours and 47 minutes including the ocular inspection.
Note: Waiting time not included